FY 20072008 marks a major step forward in Information Technology (IT) activity-based budgeting for the campus. Integrated with the annual campus budget call, a new process was used to evaluate IT funding requests. In April, the Campus Technology Council, made up of Associate CIOs representing constituent groups on campus, evaluated 36 IT funding requests constituting more than $20 million in total need. While the CTC found value in each request, limited resources necessitated a prioritization process to identify the projects with the greatest strategic alignment and campus impact. The campus Chief Information Officer Shelton Waggener used the CTC's evaluation and priorities to inform the funding recommendations he submitted to the Chancellor, who then made the final funding decisions and created an IT Bank from which the selected requests were funded.
The requests chosen for investment this year reflect support for a range of integrated technology projects which address the critical areas identified by the IT Strategic Plan:
Research: $954,000
Teaching and Learning: $1,075,000
Student Experience: $1,600,000
Administration: $796,000
Security and Reliability: $1,145,000
Governance: $180,000
-----------------------------
Total: $5,750,000
Allocations from the IT Bank for FY 20072008 have been approved as temporary funding, as shown in the table below. Note that lack of an allocation from the IT Bank for these projects does not necessarily mean that the project will not move forward. Some units have chosen to proceed with their projects using funding from other sources.
For more information on a project, please contact the project sponsor listed on the original funding request. To view the funding request detail, click on the funding request proposal title.
| CTC Request Number | Control Unit | Proposal Title | Chancellor's FY 200607 Allocation | FY 200708 | |||
|---|---|---|---|---|---|---|---|
| Central Campus IT Funding Request | Final Allocation (from IT Bank) | ||||||
| Temporary | Permanent | Total | |||||
| 1 | VCAdministration | HRMS Upgrade | $588,965 | $0 | $588,965 | $500,000 | |
| 2 | VCAdministration | Hyperion System 9 Enablement License | $125,000 | $0 | $125,000 | $0 | |
| 3 | VCAdministration | eProcurement (note: amounts reflect a VC-Admin summary spreadsheet) | $502,000 | $605,000 | $1,107,000 | $0 | |
| 4 | VCAdministration | Data Integration Foundation | $332,000 | $103,647 | $435,647 | $180,000 | |
| 5 | VCAdministration | HRMS Incremental for IST Infrastructure Services | $290,000 | $343,200 | $0 | $343,200 | $0 |
| 6 | VCAdministration | Add Student Data to Enterprise Data Warehouse | $196,690 | $64,575 | $261,265 | $116,000 | |
| VC-Administration Totals | $290,000 | $2,087,855 | $733,222 | $2,861,077 | $796,000 | ||
| 7 | Exec VC & Provost | Multi-investigator Life Sciences Computing Cluster | $1,171,000 | $0 | $1,171,000 | $350,000** | |
| 8 | Exec VC & Provost | Ubiquitous Wireless Network Pilot | $490,260 | $0 | $490,260 | see Note 1 | |
| 9 | Exec VC & Provost | CAD/CAM & Computing Laboratories | $200,380 | $122,750 | $323,130 | $0 | |
| 10 | Exec VC & Provost | Geographic Information Science Center (GISC) | $0 | $250,478 | $250,478 | $0 | |
| 11 | Exec VC & Provost | GradLink-On-the-Web | $108,900 | $0 | $108,900 | $0 | |
| 12 | Exec VC & Provost | CNR Medium-Sized Computing Cluster | $228,950 | $0 | $228,950 | ** | |
| 13 | Exec VC & Provost | Admissions Document Imaging Solution | $85,000 | $0 | $85,000 | $0 | |
| 14 | Exec VC & Provost | Secure Systems Intranet Development Project: A Research Portal | $48,400 | $0 | $48,400 | $0 | |
| 15 | Exec VC & Provost | Retiree Work Opportunities Program | $0 | $30,000 | $30,000 | $0 | |
| 16 | Exec VC & Provost | ETS Classroom Technology Operating Budget | $480K for classroom tech staffing | $0 | $647,350 | $647,350 | $470,000 |
| 17 | Exec VC & Provost | Classroom Technology Installations | $1,000,000 | $0 | $1,000,000 | See Note 2 | |
| 18 | Exec VC & Provost | bSpace Operating Budget | $580,000 | $0 | $515,000 | $515,000 | $570,000 |
| 19 | Exec VC & Provost | webcast.berkeley Program | $93,500 | $317,162 | $410,662 | ||
| 20 | Exec VC & Provost | webcast.berkeley Course Capture Support | $0 | $50,000 | $50,000 | $0 | |
| EVCP Totals | $580,000 | $3,426,390 | $1,932,740 | $5,359,130 | $1,390,000 | ||
| 21 | AVC-IT & CIO | Systems & Network Security Group: Base & Projects 1-2 | $960,000 | $0 | $1,110,682 | $1,110,682 | $980,000 |
| 22 | AVC-IT & CIO | Comprehensive Security Proposal Group A | $0 | $487,226 | $159,194 | $646,420 | $0 |
| 23 | AVC-IT & CIO | Comprehensive Security Proposal Group B | $0 | $1,345,396 | $414,910 | $1,760,306 | $0 |
| 24 | AVC-IT & CIO | IST Business Resumption | $220,000 | $943,000 | $360,100 | $1,303,100 | $130,000 |
| 25 | AVC-IT & CIO | AirBears Everywhere in 5 Years | $0 | $508,367 | $85,936 | $594,303 | See Note 1 |
| 26 | AVC-IT & CIO | Enterprise Support Ticketing System | $0 | $493,200 | $101,204 | $594,404 | $0 |
| 27 | AVC-IT & CIO | IT Governance | $150,000 | $204,562 | $28,550 | $233,112 | $180,000 |
| 28 | AVC-IT & CIO | Subversion Code Repository Service | $0 | $32,455 | $35,537 | $67,992 | $0 |
| 29 | AVC-IT & CIO | Data Management Governance | $0 | $0 | $311,775 | $311,775 | $35,000 |
| 30 | AVC-IT & CIO | Periweb Replacement | $0 | $363,313 | $0 | $363,313 | $0 |
| 31 | AVC-IT & CIO | Faculty Advancement Support Technology (FAST) | $0 | $509,041 | $0 | $509,041 | $35,000 |
| 32 | AVC-IT & CIO | Network Infrastructure with 25% rate increase | $1,200,000 | $1,411,665 | $0 | $1,411,665 | See Note 1 |
| AVC-IT & CIO Total | $2,530,000 | $6,298,225 | $2,607,888 | $8,906,113 | $1,360,000 | ||
| 33 | VC-Research | SPO COEUS Upgrade | $200,000 | $132,130 | $49,490 | $181,620 | $182,000 |
| 34 | VC-Research | Stewardship & Sharing of Digital Assets of the Berkeley Natural History Museums: A Model for Research, Phase II | $110,000 | $634,158 | $0 | $634,158 | $200,000 |
| 35 | VC-Research | IRB/IACUC Research Compliance Management System (eProtocol) | $0 | $222,050 | $0 | $222,050 | $222,000 |
| VC-Research Total | $310,000 | $988,338 | $49,490 | $1,037,828 | $604,000 | ||
| 36 | VC-Student Affairs | Student Systems 2012 | $520,000 | $2,109,306 | $86,910 | $2,196,216 | $1,600,000 |
| VC-Student Affairs Total | $520,000 | $2,109,306 | $86,910 | $2,196,216 | $1,600,000 | ||
| Chancellor's FY 2006-07 Allocation* | FY 200708 | ||||||
| Central campus request | Allocation | ||||||
| Temporary | Permanent | Total | |||||
| Total All Requests | $5,270,000 | $14,910,114 | $5,450,250 | $20,360,364 | $5,750,000*** | ||
* Chancellor's FY 0607 Allocation does not include Classroom Tech Staffing (part of proposal #16).
** The two high-performance computing cluster requests (#7 and #12) were included in the existing campus High Performance Computing Cluster project, which received $350,000 to support these and other campus high-performance computing research needs.
*** Note that $250,000 of the $6M IT Bank allocation for FY 200708 was held in reserve for urgent needs. As of April 2008, $116,000 of this reserve has been allocated to Wide Area Response Notification (WARN).
Note 1: A new funding model for voice- and data networkrelated costs will be developed over the 200708 fiscal year and is expected to be in place by FY 200809.