FY 2007–08 IT Funding Request Outcomes

FY 2007–2008 marks a major step forward in Information Technology (IT) activity-based budgeting for the campus. Integrated with the annual campus budget call, a new process was used to evaluate IT funding requests. In April, the Campus Technology Council, made up of Associate CIOs representing constituent groups on campus, evaluated 36 IT funding requests constituting more than $20 million in total need. While the CTC found value in each request, limited resources necessitated a prioritization process to identify the projects with the greatest strategic alignment and campus impact. The campus Chief Information Officer Shelton Waggener used the CTC's evaluation and priorities to inform the funding recommendations he submitted to the Chancellor, who then made the final funding decisions and created an IT Bank from which the selected requests were funded.

The requests chosen for investment this year reflect support for a range of integrated technology projects which address the critical areas identified by the IT Strategic Plan:

Research: $954,000
Teaching and Learning: $1,075,000
Student Experience: $1,600,000
Administration: $796,000
Security and Reliability: $1,145,000
Governance: $180,000
-----------------------------
Total: $5,750,000

Allocations from the IT Bank for FY 2007–2008 have been approved as temporary funding, as shown in the table below. Note that lack of an allocation from the IT Bank for these projects does not necessarily mean that the project will not move forward. Some units have chosen to proceed with their projects using funding from other sources.

For more information on a project, please contact the project sponsor listed on the original funding request. To view the funding request detail, click on the funding request proposal title.

CTC Request Number Control Unit Proposal Title Chancellor's FY 2006–07 Allocation FY 2007–08
Central Campus IT Funding Request Final Allocation (from IT Bank)
Temporary Permanent Total
1 VC–Administration HRMS Upgrade $588,965 $0 $588,965 $500,000
2 VC–Administration Hyperion System 9 Enablement License $125,000 $0 $125,000 $0
3 VC–Administration eProcurement (note: amounts reflect a VC-Admin summary spreadsheet) $502,000 $605,000 $1,107,000 $0
4 VC–Administration Data Integration Foundation $332,000 $103,647 $435,647 $180,000
5 VC–Administration HRMS Incremental for IST Infrastructure Services $290,000 $343,200 $0 $343,200 $0
6 VC–Administration Add Student Data to Enterprise Data Warehouse $196,690 $64,575 $261,265 $116,000
VC-Administration Totals $290,000 $2,087,855 $733,222 $2,861,077 $796,000
7 Exec VC & Provost Multi-investigator Life Sciences Computing Cluster $1,171,000 $0 $1,171,000 $350,000**
8 Exec VC & Provost Ubiquitous Wireless Network Pilot $490,260 $0 $490,260 see Note 1
9 Exec VC & Provost CAD/CAM & Computing Laboratories $200,380 $122,750 $323,130 $0
10 Exec VC & Provost Geographic Information Science Center (GISC) $0 $250,478 $250,478 $0
11 Exec VC & Provost GradLink-on-the-Web $108,900 $0 $108,900 $0
12 Exec VC & Provost CNR Medium-Sized Computing Cluster $228,950 $0 $228,950 **
13 Exec VC & Provost Admissions Document Imaging Solution $85,000 $0 $85,000 $0
14 Exec VC & Provost Secure Systems Intranet Development Project: A Research Portal $48,400 $0 $48,400 $0
15 Exec VC & Provost Retiree Work Opportunities Program $0 $30,000 $30,000 $0
16 Exec VC & Provost ETS Classroom Technology Operating Budget $480K for classroom tech staffing $0 $647,350 $647,350 $470,000
17 Exec VC & Provost Classroom Technology Installations $1,000,000 $0 $1,000,000 See Note 2
18 Exec VC & Provost bSpace Operating Budget $580,000 $0 $515,000 $515,000 $570,000
19 Exec VC & Provost webcast.berkeley Program $93,500 $317,162 $410,662
20 Exec VC & Provost webcast.berkeley Course Capture Support $0 $50,000 $50,000 $0
EVCP Totals $580,000 $3,426,390 $1,932,740 $5,359,130 $1,390,000
21 AVC-IT & CIO Systems & Network Security Group: Base & Projects 1-2 $960,000 $0 $1,110,682 $1,110,682 $980,000
22 AVC-IT & CIO Comprehensive Security Proposal Group A $0 $487,226 $159,194 $646,420 $0
23 AVC-IT & CIO Comprehensive Security Proposal Group B $0 $1,345,396 $414,910 $1,760,306 $0
24 AVC-IT & CIO IST Business Resumption $220,000 $943,000 $360,100 $1,303,100 $130,000
25 AVC-IT & CIO AirBears Everywhere in 5 Years $0 $508,367 $85,936 $594,303 See Note 1
26 AVC-IT & CIO Enterprise Support Ticketing System $0 $493,200 $101,204 $594,404 $0
27 AVC-IT & CIO IT Governance $150,000 $204,562 $28,550 $233,112 $180,000
28 AVC-IT & CIO Subversion Code Repository Service $0 $32,455 $35,537 $67,992 $0
29 AVC-IT & CIO Data Management Governance $0 $0 $311,775 $311,775 $35,000
30 AVC-IT & CIO Periweb Replacement $0 $363,313 $0 $363,313 $0
31 AVC-IT & CIO Faculty Advancement Support Technology (FAST) $0 $509,041 $0 $509,041 $35,000
32 AVC-IT & CIO Network Infrastructure with 25% rate increase $1,200,000 $1,411,665 $0 $1,411,665 See Note 1
AVC-IT & CIO Total $2,530,000 $6,298,225 $2,607,888 $8,906,113 $1,360,000
33 VC-Research SPO COEUS Upgrade $200,000 $132,130 $49,490 $181,620 $182,000
34 VC-Research Stewardship & Sharing of Digital Assets of the Berkeley Natural History Museums: A Model for Research, Phase II $110,000 $634,158 $0 $634,158 $200,000
35 VC-Research IRB/IACUC Research Compliance Management System (eProtocol) $0 $222,050 $0 $222,050 $222,000
VC-Research Total $310,000 $988,338 $49,490 $1,037,828 $604,000
36 VC-Student Affairs Student Systems 2012 $520,000 $2,109,306 $86,910 $2,196,216 $1,600,000
VC-Student Affairs Total $520,000 $2,109,306 $86,910 $2,196,216 $1,600,000
Chancellor's FY 2006-07 Allocation* FY 2007–08
Central campus request Allocation
Temporary Permanent Total
Total All Requests $5,270,000 $14,910,114 $5,450,250 $20,360,364 $5,750,000***

* Chancellor's FY 06–07 Allocation does not include Classroom Tech Staffing (part of proposal #16).

** The two high-performance computing cluster requests (#7 and #12) were included in the existing campus High Performance Computing Cluster project, which received $350,000 to support these and other campus high-performance computing research needs.

*** Note that $250,000 of the $6M IT Bank allocation for FY 2007–08 was held in reserve for urgent needs. As of April 2008, $116,000 of this reserve has been allocated to Wide Area Response Notification (WARN).

Note 1: A new funding model for voice- and data network–related costs will be developed over the 2007–08 fiscal year and is expected to be in place by FY 2008–09.

Note 2: $1,000,000 for classroom upgrades will be provided for FY 2007–08 out of a separate allocation that has committed $5,000,000 over 5 years to upgrading classrooms.

Questions? Please contact Susan McKeehan, Office of the CIO Financial Planning and Technology Investment Services (FPTIS), 642-8874, or Dianne Walker, 643-0290.

 